Pinnacle Hotels Engineering
Pinnacle Hotel, back-of-house plant room
1 Circular Quay West, Sydney NSW 2000
- Location
- Sydney
- Assets
- 4
- Service
- 1 due soon
Open work at this Site
0 open jobs, plus 0 quotes out worth $0, ex GST
Map and access
Access notes
Sign in at the loading dock security desk. Induction card required. Plant room key from the building manager.
Contacts
Marcus Oyelaran
Chief engineer, Pinnacle Hotels Engineering
Neil Fairbairn
Purchasing manager, Pinnacle Hotels Engineering
Assets
| Tag | Asset | Make and model | Serial | Position | Installed | Next service | Jobs |
|---|---|---|---|---|---|---|---|
| CHWP-01 | CHW pumpHVAC | Armstrong 4300 Vertical In-Line | ARCH-200146 | Plant room | 2016 | 07/11/2026Due soon | 10462 |
| AHU-01 | AHUHVAC | Daikin D-AHU Modular | DAAH-211819 | Rooftop plant | 2019 | 29/12/2026 | None |
| CH-01 | ChillerHVAC | Daikin EWAD-TZ | DACH-223492 | Rooftop plant | 2022 | 26/11/2026 | None |
| EF-01 | Exhaust fanHVAC | Fantech AP0804AP | FAEF-235165 | Car park | 2010 | 23/12/2026 | None |
4 Assets. Due soon means within 14 days.
Service Agreements
No Service Agreement covers this Site. Maintenance here is billed per Job.
Certificates
All Certificates- CERT-00461AS 1668.1:2015, 1 Asset tested 26/06/2026Fail
- CERT-00423AS 1668.1:2015, 1 Asset tested 26/12/2025Pass
Jobs at this Site
| Job | Title | Status | Value |
|---|---|---|---|
| 10462 | CHW pump seal kit replacement | Invoiced | $8,000 |
1 job. Values are ex GST.
Quotes at this Site
| JN | Quote | Status | Due | Value |
|---|---|---|---|---|
| 10473 | CHW pump seal kit replacement | Won | 27/09/2026 | $8,000 |