Money

Progress Claims

MS

Progress Claims

Progress Claim PC-10456-01

Approved

Job 10456, Mechanical services, Levels 3 to 8 fit-out

Westmoor Constructions, attention Angela Papadakis. Subcontract WC-SC-2214. Westmoor Tower, Levels 3 to 8, 50 Bridge St, Sydney NSW 2000

Paid throughInvoice INV-20334Paid$0.00 owing

Period ending
25/06/2026
Submitted
25/06/2026
Payment schedule due
09/07/2026
Payment due
23/07/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries and site establishment$24,300.000%$0.0060%$14,580.0060%$14,580.00$9,720.00
2Shop drawings and submissions$14,600.000%$0.0080%$11,680.0080%$11,680.00$2,920.00
3Ductwork, supply and install$132,800.000%$0.0010%$13,280.0010%$13,280.00$119,520.00
4Chilled and heating water pipework$98,400.000%$0.005%$4,920.005%$4,920.00$93,480.00
5Fan coil units and VAV boxes$86,200.000%$0.000%$0.000%$0.00$86,200.00
6Grilles, registers and diffusers$31,500.000%$0.000%$0.000%$0.00$31,500.00
7Controls and BMS integration$48,900.000%$0.000%$0.000%$0.00$48,900.00
8Commissioning and air balancing$26,700.000%$0.000%$0.000%$0.00$26,700.00
9O&M manuals and as-built drawings$9,800.000%$0.000%$0.000%$0.00$9,800.00
10Defects and handover$12,800.000%$0.000%$0.000%$0.00$12,800.00
Contract works subtotal$486,000.00$0.00$44,460.00$44,460.00$441,540.00
Accepted Variations
No Variations accepted by the end of this period.
Total$486,000.00$0.00$44,460.00$44,460.00$441,540.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$486,000.00
Accepted Variations
$0.00
Revised contract sum
$486,000.00
Work completed to date (9.1%)
$44,460.00
Less work previously claimed
$0.00
Value of work this claim
$44,460.00
Less Retention held this claim
-$4,446.00
Amount of this claim, ex GST
$40,014.00
GST (10%)
$4,001.40
Amount due, inc GST
$44,015.40

Certified $40,014.00 ex GST, $44,015.40 inc GST, in full

Retention

Terms
10% of the value of work to date, capped at 5% of the contract sum
Cap
$24,300.00
Held before this claim
$0.00
Held after this claim
$4,446.00
Released at practical completion
50%, $2,223.00
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10456-0125/06/2026, Approved$40,014.00$44,460.00

This claim is ex GST, after Retention. To date is work completed, before Retention.