Progress Claim PC-10458-01

Approved

Job 10458, Fire services, Block D science building

Tallowood Education Facilities, attention Hamish Greer. Subcontract TEF-D-0457. Tallowood College, Block D, 40 University Dr, St Lucia QLD 4067

Paid throughInvoice INV-20339Paid$0.00 owing

Period ending
25/08/2026
Submitted
25/08/2026
Payment schedule due
15/09/2026
Payment due
29/09/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries and design$16,800.000%$0.0070%$11,760.0070%$11,760.00$5,040.00
2Sprinkler mains and risers$52,400.000%$0.0040%$20,960.0040%$20,960.00$31,440.00
3Sprinkler range pipework and heads$61,300.000%$0.0010%$6,130.0010%$6,130.00$55,170.00
4Fire hydrants and hose reels$24,700.000%$0.000%$0.000%$0.00$24,700.00
5Detection and fire indicator panel$38,200.000%$0.000%$0.000%$0.00$38,200.00
6Emergency warning system (EWIS)$14,600.000%$0.000%$0.000%$0.00$14,600.00
7Commissioning and certification$6,800.000%$0.000%$0.000%$0.00$6,800.00
Contract works subtotal$214,800.00$0.00$38,850.00$38,850.00$175,950.00
Accepted Variations
No Variations accepted by the end of this period.
Total$214,800.00$0.00$38,850.00$38,850.00$175,950.00

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). This claim requests payment of the claimed amount.

Claim summary

Contract sum
$214,800.00
Accepted Variations
$0.00
Revised contract sum
$214,800.00
Work completed to date (18.1%)
$38,850.00
Less work previously claimed
$0.00
Value of work this claim
$38,850.00
Less Retention held this claim
-$3,885.00
Amount of this claim, ex GST
$34,965.00
GST (10%)
$3,496.50
Amount due, inc GST
$38,461.50

Certified $34,965.00 ex GST, $38,461.50 inc GST, in full

Retention

Terms
10% of the value of work to date, capped at 5% of the contract sum
Cap
$10,740.00
Held before this claim
$0.00
Held after this claim
$3,885.00
Released at practical completion
50%, $1,942.50
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10458-0125/08/2026, Approved$34,965.00$38,850.00

This claim is ex GST, after Retention. To date is work completed, before Retention.