Progress Claim PC-10459-02

Approved

Job 10459, Mechanical services refurbishment, Levels 1 to 4

Parkside Developments, attention Nadia Kowalczyk. Subcontract PD-MECH-031. Parkside Commerce Centre, Levels 1 to 4, 9 Parkside Ave, Macquarie Park NSW 2113

Paid throughInvoice INV-20342Paid$0.00 owing

Period ending
25/06/2026
Submitted
25/06/2026
Payment schedule due
09/07/2026
Payment due
23/07/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$13,400.0050%$6,700.0020%$2,680.0070%$9,380.00$4,020.00
2Strip-out and make safe$18,600.00100%$18,600.000%$0.00100%$18,600.00$0.00
3Ductwork modifications$64,200.0020%$12,840.0035%$22,470.0055%$35,310.00$28,890.00
4AHU replacement, 2 units$92,500.000%$0.0030%$27,750.0030%$27,750.00$64,750.00
5Controls upgrade$41,800.000%$0.000%$0.000%$0.00$41,800.00
6Commissioning and air balancing$22,700.000%$0.000%$0.000%$0.00$22,700.00
7Handover and O&M manuals$14,800.000%$0.000%$0.000%$0.00$14,800.00
Contract works subtotal$268,000.00$38,140.00$52,900.00$91,040.00$176,960.00
Accepted Variations
No Variations accepted by the end of this period.
Total$268,000.00$38,140.00$52,900.00$91,040.00$176,960.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$268,000.00
Accepted Variations
$0.00
Revised contract sum
$268,000.00
Work completed to date (34%)
$91,040.00
Less work previously claimed
-$38,140.00
Value of work this claim
$52,900.00
Less Retention held this claim
-$2,645.00
Amount of this claim, ex GST
$50,255.00
GST (10%)
$5,025.50
Amount due, inc GST
$55,280.50

Certified $50,255.00 ex GST, $55,280.50 inc GST, in full

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$13,400.00
Held before this claim
$1,907.00
Held after this claim
$4,552.00
Released at practical completion
50%, $2,276.00
Rest at the end of the defects period
50%, 11/09/2027
Practical completion
11/09/2026

Claim history

ClaimThis claimTo date
PC-10459-0125/05/2026, Approved$36,233.00$38,140.00
PC-10459-0225/06/2026, Approved$50,255.00$91,040.00

This claim is ex GST, after Retention. To date is work completed, before Retention.