Progress Claim PC-10456-03

Approved

Job 10456, Mechanical services, Levels 3 to 8 fit-out

Westmoor Constructions, attention Angela Papadakis. Subcontract WC-SC-2214. Westmoor Tower, Levels 3 to 8, 50 Bridge St, Sydney NSW 2000

Paid throughInvoice INV-20336Paid$0.00 owing

Period ending
25/08/2026
Submitted
25/08/2026
Payment schedule due
08/09/2026
Payment due
22/09/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries and site establishment$24,300.0075%$18,225.0010%$2,430.0085%$20,655.00$3,645.00
2Shop drawings and submissions$14,600.00100%$14,600.000%$0.00100%$14,600.00$0.00
3Ductwork, supply and install$132,800.0030%$39,840.0025%$33,200.0055%$73,040.00$59,760.00
4Chilled and heating water pipework$98,400.0020%$19,680.0020%$19,680.0040%$39,360.00$59,040.00
5Fan coil units and VAV boxes$86,200.0010%$8,620.0020%$17,240.0030%$25,860.00$60,340.00
6Grilles, registers and diffusers$31,500.000%$0.005%$1,575.005%$1,575.00$29,925.00
7Controls and BMS integration$48,900.000%$0.0010%$4,890.0010%$4,890.00$44,010.00
8Commissioning and air balancing$26,700.000%$0.000%$0.000%$0.00$26,700.00
9O&M manuals and as-built drawings$9,800.000%$0.000%$0.000%$0.00$9,800.00
10Defects and handover$12,800.000%$0.000%$0.000%$0.00$12,800.00
Contract works subtotal$486,000.00$100,965.00$79,015.00$179,980.00$306,020.00
Accepted Variations
V01Additional FCU, Level 5 comms room$18,450.000%$0.0020%$3,690.0020%$3,690.00$14,760.00
Variations subtotal$18,450.00$0.00$3,690.00$3,690.00$14,760.00
Total$504,450.00$100,965.00$82,705.00$183,670.00$320,780.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$486,000.00
Accepted Variations
$18,450.00
Revised contract sum
$504,450.00
Work completed to date (36.4%)
$183,670.00
Less work previously claimed
-$100,965.00
Value of work this claim
$82,705.00
Less Retention held this claim
-$8,270.50
Amount of this claim, ex GST
$74,434.50
GST (10%)
$7,443.45
Amount due, inc GST
$81,877.95

Certified $74,434.50 ex GST, $81,877.95 inc GST, in full

Retention

Terms
10% of the value of work to date, capped at 5% of the contract sum
Cap
$24,300.00
Held before this claim
$10,096.50
Held after this claim
$18,367.00
Released at practical completion
50%, $9,183.50
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10456-0125/06/2026, Approved$40,014.00$44,460.00
PC-10456-0224/07/2026, Approved$50,854.50$100,965.00
PC-10456-0325/08/2026, Approved$74,434.50$183,670.00

This claim is ex GST, after Retention. To date is work completed, before Retention.