Progress Claim PC-10457-01

Approved

Job 10457, Electrical services, Stage 2 warehouse

Brightwater Builders, attention Sam Teasdale. Subcontract BB-2026-118. Brightwater Logistics Hub, Stage 2, 14 Industry Dr, Eagle Farm QLD 4009

Paid throughInvoice INV-20338Paid$0.00 owing

Period ending
24/07/2026
Submitted
24/07/2026
Payment schedule due
14/08/2026
Payment due
28/08/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$12,500.000%$0.0050%$6,250.0050%$6,250.00$6,250.00
2Consumer mains and main switchboard$46,800.000%$0.0020%$9,360.0020%$9,360.00$37,440.00
3Distribution boards$28,400.000%$0.000%$0.000%$0.00$28,400.00
4Cable tray and containment$39,200.000%$0.0030%$11,760.0030%$11,760.00$27,440.00
5Sub-mains and final subcircuits$64,300.000%$0.000%$0.000%$0.00$64,300.00
6High-bay and external lighting$71,600.000%$0.000%$0.000%$0.00$71,600.00
7Emergency and exit lighting$18,900.000%$0.000%$0.000%$0.00$18,900.00
8Data and security rough-in$17,600.000%$0.000%$0.000%$0.00$17,600.00
9Testing, commissioning and certification$13,200.000%$0.000%$0.000%$0.00$13,200.00
Contract works subtotal$312,500.00$0.00$27,370.00$27,370.00$285,130.00
Accepted Variations
No Variations accepted by the end of this period.
Total$312,500.00$0.00$27,370.00$27,370.00$285,130.00

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). This claim requests payment of the claimed amount.

Claim summary

Contract sum
$312,500.00
Accepted Variations
$0.00
Revised contract sum
$312,500.00
Work completed to date (8.8%)
$27,370.00
Less work previously claimed
$0.00
Value of work this claim
$27,370.00
Less Retention held this claim
-$1,368.50
Amount of this claim, ex GST
$26,001.50
GST (10%)
$2,600.15
Amount due, inc GST
$28,601.65

Certified $26,001.50 ex GST, $28,601.65 inc GST, in full

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$15,625.00
Held before this claim
$0.00
Held after this claim
$1,368.50
Released at practical completion
50%, $684.25
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10457-0124/07/2026, Approved$26,001.50$27,370.00

This claim is ex GST, after Retention. To date is work completed, before Retention.