Job 10457
In progressNormalElectrical services, Stage 2 warehouse
Brightwater BuildersBrightwater Logistics Hub, Stage 2, 14 Industry Dr, Eagle Farm QLD 4009Project P-102
Raise variation
- Due
- 11/12/2026
- Location
- Brisbane
- Contact
- Sam Teasdale
Scope of works
Electrical services, Stage 2 warehouse at Brightwater Logistics Hub, Stage 2. Works as per the accepted quote, carried out during agreed access hours with isolation and permits by the site contact. Any variation is raised before the work goes ahead.
- Client
- Brightwater Builders
- Type
- Electrical
- Priority
- Normal
- Due
- 11/12/2026
- Site
- Brightwater Logistics Hub, Stage 2
- Address
- 14 Industry Dr, Eagle Farm QLD 4009
Contract value
$326,780
ex GST
- Original quote
- $312,500
- Accepted Variations (1)
- +$14,280
$64,765 cost, 20% used$262,015 left
- Bills in the cost to date
- $63,040
- Committed on Purchase Orders
- $9,600
- Left after commitments
- $252,415
- GST (10%)
- $32,678
- Contract inc GST
- $359,458
Assigned techs
- Sienna WalshSienna WalshElectrical, Brisbane
Activity
Work started on site
28/10/2026
Scheduled and techs assigned
24/10/2026
Client purchase order received
21/10/2026
Job created from won quote via Claude
19/10/2026