Progress Claim PC-10458-02

Approved

Job 10458, Fire services, Block D science building

Tallowood Education Facilities, attention Hamish Greer. Subcontract TEF-D-0457. Tallowood College, Block D, 40 University Dr, St Lucia QLD 4067

Paid throughInvoice INV-20340Unpaid$61,028.55 owing

Period ending
25/09/2026
Submitted
25/09/2026
Payment schedule due
19/10/2026
Payment due
02/11/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries and design$16,800.0070%$11,760.0020%$3,360.0090%$15,120.00$1,680.00
2Sprinkler mains and risers$52,400.0040%$20,960.0040%$20,960.0080%$41,920.00$10,480.00
3Sprinkler range pipework and heads$61,300.0010%$6,130.0035%$21,455.0045%$27,585.00$33,715.00
4Fire hydrants and hose reels$24,700.000%$0.0030%$7,410.0030%$7,410.00$17,290.00
5Detection and fire indicator panel$38,200.000%$0.0020%$7,640.0020%$7,640.00$30,560.00
6Emergency warning system (EWIS)$14,600.000%$0.000%$0.000%$0.00$14,600.00
7Commissioning and certification$6,800.000%$0.000%$0.000%$0.00$6,800.00
Contract works subtotal$214,800.00$38,850.00$60,825.00$99,675.00$115,125.00
Accepted Variations
V01Extra sprinkler heads, Lab 2 ceiling change$6,950.000%$0.00100%$6,950.00100%$6,950.00$0.00
Variations subtotal$6,950.00$0.00$6,950.00$6,950.00$0.00
Total$221,750.00$38,850.00$67,775.00$106,625.00$115,125.00

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). This claim requests payment of the claimed amount.

Claim summary

Contract sum
$214,800.00
Accepted Variations
$6,950.00
Revised contract sum
$221,750.00
Work completed to date (48.1%)
$106,625.00
Less work previously claimed
-$38,850.00
Value of work this claim
$67,775.00
Less Retention held this claim
-$6,777.50
Amount of this claim, ex GST
$60,997.50
GST (10%)
$6,099.75
Amount due, inc GST
$67,097.25

Certified $55,480.50 ex GST, $61,028.55 inc GST on 07/10/2026

$5,517.00 withheld. Builder values sprinkler range pipework at 35% complete, not 45%.

Retention

Terms
10% of the value of work to date, capped at 5% of the contract sum
Cap
$10,740.00
Held before this claim
$3,885.00
Held after this claim
$10,662.50
Released at practical completion
50%, $5,331.25
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10458-0125/08/2026, Approved$34,965.00$38,850.00
PC-10458-0225/09/2026, Approved$60,997.50$106,625.00

This claim is ex GST, after Retention. To date is work completed, before Retention.