Progress Claims
Progress Claim PC-10459-03
ApprovedJob 10459, Mechanical services refurbishment, Levels 1 to 4
Parkside Developments, attention Nadia Kowalczyk. Subcontract PD-MECH-031. Parkside Commerce Centre, Levels 1 to 4, 9 Parkside Ave, Macquarie Park NSW 2113
Paid throughInvoice INV-20343Paid$0.00 owing
- Period ending
- 24/07/2026
- Submitted
- 24/07/2026
- Payment schedule due
- 07/08/2026
- Payment due
- 21/08/2026
Claim schedule
| Previously claimed | This claim | Complete to date | |||||||
|---|---|---|---|---|---|---|---|---|---|
| Item | Description | Value | % | $ | % | $ | % | $ | Balance |
| Contract works | |||||||||
| 1 | Preliminaries | $13,400.00 | 70% | $9,380.00 | 15% | $2,010.00 | 85% | $11,390.00 | $2,010.00 |
| 2 | Strip-out and make safe | $18,600.00 | 100% | $18,600.00 | 0% | $0.00 | 100% | $18,600.00 | $0.00 |
| 3 | Ductwork modifications | $64,200.00 | 55% | $35,310.00 | 30% | $19,260.00 | 85% | $54,570.00 | $9,630.00 |
| 4 | AHU replacement, 2 units | $92,500.00 | 30% | $27,750.00 | 40% | $37,000.00 | 70% | $64,750.00 | $27,750.00 |
| 5 | Controls upgrade | $41,800.00 | 0% | $0.00 | 40% | $16,720.00 | 40% | $16,720.00 | $25,080.00 |
| 6 | Commissioning and air balancing | $22,700.00 | 0% | $0.00 | 0% | $0.00 | 0% | $0.00 | $22,700.00 |
| 7 | Handover and O&M manuals | $14,800.00 | 0% | $0.00 | 0% | $0.00 | 0% | $0.00 | $14,800.00 |
| Contract works subtotal | $268,000.00 | $91,040.00 | $74,990.00 | $166,030.00 | $101,970.00 | ||||
| Accepted Variations | |||||||||
| V01 | Replace corroded condensate trays, AHU 2 | $7,640.00 | 0% | $0.00 | 50% | $3,820.00 | 50% | $3,820.00 | $3,820.00 |
| Variations subtotal | $7,640.00 | $0.00 | $3,820.00 | $3,820.00 | $3,820.00 | ||||
| Total | $275,640.00 | $91,040.00 | $78,810.00 | $169,850.00 | $105,790.00 | ||||
This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).
Claim summary
- Contract sum
- $268,000.00
- Accepted Variations
- $7,640.00
- Revised contract sum
- $275,640.00
- Work completed to date (61.6%)
- $169,850.00
- Less work previously claimed
- -$91,040.00
- Value of work this claim
- $78,810.00
- Less Retention held this claim
- -$3,940.50
- Amount of this claim, ex GST
- $74,869.50
- GST (10%)
- $7,486.95
- Amount due, inc GST
- $82,356.45
Certified $74,869.50 ex GST, $82,356.45 inc GST, in full
Retention
- Terms
- 5% of the value of work to date, capped at 5% of the contract sum
- Cap
- $13,400.00
- Held before this claim
- $4,552.00
- Held after this claim
- $8,492.50
- Released at practical completion
- 50%, $4,246.25
- Rest at the end of the defects period
- 50%, 11/09/2027
- Practical completion
- 11/09/2026
Claim history
| Claim | This claim | To date |
|---|---|---|
| PC-10459-0125/05/2026, Approved | $36,233.00 | $38,140.00 |
| PC-10459-0225/06/2026, Approved | $50,255.00 | $91,040.00 |
| PC-10459-0324/07/2026, Approved | $74,869.50 | $169,850.00 |
This claim is ex GST, after Retention. To date is work completed, before Retention.