Money

Progress Claims

MS

Progress Claims

Progress Claim PC-10456-04

Approved

Job 10456, Mechanical services, Levels 3 to 8 fit-out

Westmoor Constructions, attention Angela Papadakis. Subcontract WC-SC-2214. Westmoor Tower, Levels 3 to 8, 50 Bridge St, Sydney NSW 2000

Paid throughInvoice INV-20337Overdue$83,459.20 owing

Period ending
25/09/2026
Submitted
25/09/2026
Payment schedule due
12/10/2026
Payment due
26/10/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries and site establishment$24,300.0085%$20,655.005%$1,215.0090%$21,870.00$2,430.00
2Shop drawings and submissions$14,600.00100%$14,600.000%$0.00100%$14,600.00$0.00
3Ductwork, supply and install$132,800.0055%$73,040.0015%$19,920.0070%$92,960.00$39,840.00
4Chilled and heating water pipework$98,400.0040%$39,360.0020%$19,680.0060%$59,040.00$39,360.00
5Fan coil units and VAV boxes$86,200.0030%$25,860.0025%$21,550.0055%$47,410.00$38,790.00
6Grilles, registers and diffusers$31,500.005%$1,575.0015%$4,725.0020%$6,300.00$25,200.00
7Controls and BMS integration$48,900.0010%$4,890.0015%$7,335.0025%$12,225.00$36,675.00
8Commissioning and air balancing$26,700.000%$0.000%$0.000%$0.00$26,700.00
9O&M manuals and as-built drawings$9,800.000%$0.000%$0.000%$0.00$9,800.00
10Defects and handover$12,800.000%$0.000%$0.000%$0.00$12,800.00
Contract works subtotal$486,000.00$179,980.00$74,425.00$254,405.00$231,595.00
Accepted Variations
V01Additional FCU, Level 5 comms room$18,450.0020%$3,690.0040%$7,380.0060%$11,070.00$7,380.00
Variations subtotal$18,450.00$3,690.00$7,380.00$11,070.00$7,380.00
Total$504,450.00$183,670.00$81,805.00$265,475.00$238,975.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$486,000.00
Accepted Variations
$18,450.00
Revised contract sum
$504,450.00
Work completed to date (52.6%)
$265,475.00
Less work previously claimed
-$183,670.00
Value of work this claim
$81,805.00
Less Retention held this claim
-$5,933.00
Amount of this claim, ex GST
$75,872.00
GST (10%)
$7,587.20
Amount due, inc GST
$83,459.20

Certified $75,872.00 ex GST, $83,459.20 inc GST, in full

Retention

Terms
10% of the value of work to date, capped at 5% of the contract sum
Cap
$24,300.00
Held before this claim
$18,367.00
Held after this claim
$24,300.00
Released at practical completion
50%, $12,150.00
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10456-0125/06/2026, Approved$40,014.00$44,460.00
PC-10456-0224/07/2026, Approved$50,854.50$100,965.00
PC-10456-0325/08/2026, Approved$74,434.50$183,670.00
PC-10456-0425/09/2026, Approved$75,872.00$265,475.00

This claim is ex GST, after Retention. To date is work completed, before Retention.