Progress Claims

Progress Claim PC-10457-02

Submitted

Job 10457, Electrical services, Stage 2 warehouse

Brightwater Builders, attention Sam Teasdale. Subcontract BB-2026-118. Brightwater Logistics Hub, Stage 2, 14 Industry Dr, Eagle Farm QLD 4009

No payment schedule by 15/09/2026. The builder owes the full claimed amount.

Period ending
25/08/2026
Submitted
25/08/2026
Payment schedule due
15/09/2026
Payment due
29/09/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$12,500.0050%$6,250.0020%$2,500.0070%$8,750.00$3,750.00
2Consumer mains and main switchboard$46,800.0020%$9,360.0040%$18,720.0060%$28,080.00$18,720.00
3Distribution boards$28,400.000%$0.0040%$11,360.0040%$11,360.00$17,040.00
4Cable tray and containment$39,200.0030%$11,760.0030%$11,760.0060%$23,520.00$15,680.00
5Sub-mains and final subcircuits$64,300.000%$0.0025%$16,075.0025%$16,075.00$48,225.00
6High-bay and external lighting$71,600.000%$0.000%$0.000%$0.00$71,600.00
7Emergency and exit lighting$18,900.000%$0.000%$0.000%$0.00$18,900.00
8Data and security rough-in$17,600.000%$0.000%$0.000%$0.00$17,600.00
9Testing, commissioning and certification$13,200.000%$0.000%$0.000%$0.00$13,200.00
Contract works subtotal$312,500.00$27,370.00$60,415.00$87,785.00$224,715.00
Accepted Variations
V01EV charger circuits, car park$14,280.000%$0.000%$0.000%$0.00$14,280.00
Variations subtotal$14,280.00$0.00$0.00$0.00$14,280.00
Total$326,780.00$27,370.00$60,415.00$87,785.00$238,995.00

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). This claim requests payment of the claimed amount.

Claim summary

Contract sum
$312,500.00
Accepted Variations
$14,280.00
Revised contract sum
$326,780.00
Work completed to date (26.9%)
$87,785.00
Less work previously claimed
-$27,370.00
Value of work this claim
$60,415.00
Less Retention held this claim
-$3,020.75
Amount of this claim, ex GST
$57,394.25
GST (10%)
$5,739.43
Amount due, inc GST
$63,133.68

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$15,625.00
Held before this claim
$1,368.50
Held after this claim
$4,389.25
Released at practical completion
50%, $2,194.63
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10457-0124/07/2026, Approved$26,001.50$27,370.00
PC-10457-0225/08/2026, Submitted$57,394.25$87,785.00

This claim is ex GST, after Retention. To date is work completed, before Retention.