Progress Claim PC-10459-04

Approved

Job 10459, Mechanical services refurbishment, Levels 1 to 4

Parkside Developments, attention Nadia Kowalczyk. Subcontract PD-MECH-031. Parkside Commerce Centre, Levels 1 to 4, 9 Parkside Ave, Macquarie Park NSW 2113

Paid throughInvoice INV-20344Paid$0.00 owing

Period ending
25/08/2026
Submitted
25/08/2026
Payment schedule due
08/09/2026
Payment due
22/09/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$13,400.0085%$11,390.0010%$1,340.0095%$12,730.00$670.00
2Strip-out and make safe$18,600.00100%$18,600.000%$0.00100%$18,600.00$0.00
3Ductwork modifications$64,200.0085%$54,570.0015%$9,630.00100%$64,200.00$0.00
4AHU replacement, 2 units$92,500.0070%$64,750.0030%$27,750.00100%$92,500.00$0.00
5Controls upgrade$41,800.0040%$16,720.0045%$18,810.0085%$35,530.00$6,270.00
6Commissioning and air balancing$22,700.000%$0.0060%$13,620.0060%$13,620.00$9,080.00
7Handover and O&M manuals$14,800.000%$0.000%$0.000%$0.00$14,800.00
Contract works subtotal$268,000.00$166,030.00$71,150.00$237,180.00$30,820.00
Accepted Variations
V01Replace corroded condensate trays, AHU 2$7,640.0050%$3,820.0050%$3,820.00100%$7,640.00$0.00
Variations subtotal$7,640.00$3,820.00$3,820.00$7,640.00$0.00
Total$275,640.00$169,850.00$74,970.00$244,820.00$30,820.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$268,000.00
Accepted Variations
$7,640.00
Revised contract sum
$275,640.00
Work completed to date (88.8%)
$244,820.00
Less work previously claimed
-$169,850.00
Value of work this claim
$74,970.00
Less Retention held this claim
-$3,748.50
Amount of this claim, ex GST
$71,221.50
GST (10%)
$7,122.15
Amount due, inc GST
$78,343.65

Certified $71,221.50 ex GST, $78,343.65 inc GST, in full

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$13,400.00
Held before this claim
$8,492.50
Held after this claim
$12,241.00
Released at practical completion
50%, $6,120.50
Rest at the end of the defects period
50%, 11/09/2027
Practical completion
11/09/2026

Claim history

ClaimThis claimTo date
PC-10459-0125/05/2026, Approved$36,233.00$38,140.00
PC-10459-0225/06/2026, Approved$50,255.00$91,040.00
PC-10459-0324/07/2026, Approved$74,869.50$169,850.00
PC-10459-0425/08/2026, Approved$71,221.50$244,820.00