Money

Progress Claims

MS

Progress Claims

Progress Claim PC-10456-05

Draft

Job 10456, Mechanical services, Levels 3 to 8 fit-out

Westmoor Constructions, attention Angela Papadakis. Subcontract WC-SC-2214. Westmoor Tower, Levels 3 to 8, 50 Bridge St, Sydney NSW 2000

Period ending
23/10/2026
Submitted
Not yet
Payment schedule due
-
Payment due
-

Claim schedule

Enter each line's percent complete to date. Everything else works itself out.

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries and site establishment$24,300.0090%$21,870.005%$1,215.00%$23,085.00$1,215.00
2Shop drawings and submissions$14,600.00100%$14,600.000%$0.00%$14,600.00$0.00
3Ductwork, supply and install$132,800.0070%$92,960.0015%$19,920.00%$112,880.00$19,920.00
4Chilled and heating water pipework$98,400.0060%$59,040.0015%$14,760.00%$73,800.00$24,600.00
5Fan coil units and VAV boxes$86,200.0055%$47,410.0015%$12,930.00%$60,340.00$25,860.00
6Grilles, registers and diffusers$31,500.0020%$6,300.0020%$6,300.00%$12,600.00$18,900.00
7Controls and BMS integration$48,900.0025%$12,225.0015%$7,335.00%$19,560.00$29,340.00
8Commissioning and air balancing$26,700.000%$0.000%$0.00%$0.00$26,700.00
9O&M manuals and as-built drawings$9,800.000%$0.000%$0.00%$0.00$9,800.00
10Defects and handover$12,800.000%$0.000%$0.00%$0.00$12,800.00
Contract works subtotal$486,000.00$254,405.00$62,460.00$316,865.00$169,135.00
Accepted Variations
V01Additional FCU, Level 5 comms room$18,450.0060%$11,070.0040%$7,380.00%$18,450.00$0.00
V02Relocate supply riser, Level 7$5,000.000%$0.0050%$2,500.00%$2,500.00$2,500.00
Variations subtotal$23,450.00$11,070.00$9,880.00$20,950.00$2,500.00
Total$509,450.00$265,475.00$72,340.00$337,815.00$171,635.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$486,000.00
Accepted Variations
$23,450.00
Revised contract sum
$509,450.00
Work completed to date (66.3%)
$337,815.00
Less work previously claimed
-$265,475.00
Value of work this claim
$72,340.00
Less Retention held this claim
$0.00
Amount of this claim, ex GST
$72,340.00
GST (10%)
$7,234.00
Amount due, inc GST
$79,574.00

Retention

Terms
10% of the value of work to date, capped at 5% of the contract sum
Cap
$24,300.00
Held before this claim
$24,300.00
Held after this claim
$24,300.00
Released at practical completion
50%, $12,150.00
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10456-0125/06/2026, Approved$40,014.00$44,460.00
PC-10456-0224/07/2026, Approved$50,854.50$100,965.00
PC-10456-0325/08/2026, Approved$74,434.50$183,670.00
PC-10456-0425/09/2026, Approved$75,872.00$265,475.00
PC-10456-0523/10/2026, Draft$72,340.00$337,815.00

This claim is ex GST, after Retention. To date is work completed, before Retention.