Progress Claim PC-10457-03

Submitted

Job 10457, Electrical services, Stage 2 warehouse

Brightwater Builders, attention Sam Teasdale. Subcontract BB-2026-118. Brightwater Logistics Hub, Stage 2, 14 Industry Dr, Eagle Farm QLD 4009

No payment schedule by 19/10/2026. The builder owes the full claimed amount.

Period ending
25/09/2026
Submitted
25/09/2026
Payment schedule due
19/10/2026
Payment due
02/11/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$12,500.0070%$8,750.0015%$1,875.0085%$10,625.00$1,875.00
2Consumer mains and main switchboard$46,800.0060%$28,080.0030%$14,040.0090%$42,120.00$4,680.00
3Distribution boards$28,400.0040%$11,360.0035%$9,940.0075%$21,300.00$7,100.00
4Cable tray and containment$39,200.0060%$23,520.0025%$9,800.0085%$33,320.00$5,880.00
5Sub-mains and final subcircuits$64,300.0025%$16,075.0030%$19,290.0055%$35,365.00$28,935.00
6High-bay and external lighting$71,600.000%$0.0020%$14,320.0020%$14,320.00$57,280.00
7Emergency and exit lighting$18,900.000%$0.000%$0.000%$0.00$18,900.00
8Data and security rough-in$17,600.000%$0.000%$0.000%$0.00$17,600.00
9Testing, commissioning and certification$13,200.000%$0.000%$0.000%$0.00$13,200.00
Contract works subtotal$312,500.00$87,785.00$69,265.00$157,050.00$155,450.00
Accepted Variations
V01EV charger circuits, car park$14,280.000%$0.0040%$5,712.0040%$5,712.00$8,568.00
Variations subtotal$14,280.00$0.00$5,712.00$5,712.00$8,568.00
Total$326,780.00$87,785.00$74,977.00$162,762.00$164,018.00

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). This claim requests payment of the claimed amount.

Claim summary

Contract sum
$312,500.00
Accepted Variations
$14,280.00
Revised contract sum
$326,780.00
Work completed to date (49.8%)
$162,762.00
Less work previously claimed
-$87,785.00
Value of work this claim
$74,977.00
Less Retention held this claim
-$3,748.85
Amount of this claim, ex GST
$71,228.15
GST (10%)
$7,122.82
Amount due, inc GST
$78,350.97

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$15,625.00
Held before this claim
$4,389.25
Held after this claim
$8,138.10
Released at practical completion
50%, $4,069.05
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10457-0124/07/2026, Approved$26,001.50$27,370.00
PC-10457-0225/08/2026, Submitted$57,394.25$87,785.00
PC-10457-0325/09/2026, Submitted$71,228.15$162,762.00

This claim is ex GST, after Retention. To date is work completed, before Retention.