Progress Claim PC-10459-05

Approved

Job 10459, Mechanical services refurbishment, Levels 1 to 4

Parkside Developments, attention Nadia Kowalczyk. Subcontract PD-MECH-031. Parkside Commerce Centre, Levels 1 to 4, 9 Parkside Ave, Macquarie Park NSW 2113

Paid throughInvoice INV-20345Paid$0.00 owing

Period ending
25/09/2026
Submitted
25/09/2026
Payment schedule due
12/10/2026
Payment due
26/10/2026

Claim schedule

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$13,400.0095%$12,730.005%$670.00100%$13,400.00$0.00
2Strip-out and make safe$18,600.00100%$18,600.000%$0.00100%$18,600.00$0.00
3Ductwork modifications$64,200.00100%$64,200.000%$0.00100%$64,200.00$0.00
4AHU replacement, 2 units$92,500.00100%$92,500.000%$0.00100%$92,500.00$0.00
5Controls upgrade$41,800.0085%$35,530.0015%$6,270.00100%$41,800.00$0.00
6Commissioning and air balancing$22,700.0060%$13,620.0040%$9,080.00100%$22,700.00$0.00
7Handover and O&M manuals$14,800.000%$0.00100%$14,800.00100%$14,800.00$0.00
Contract works subtotal$268,000.00$237,180.00$30,820.00$268,000.00$0.00
Accepted Variations
V01Replace corroded condensate trays, AHU 2$7,640.00100%$7,640.000%$0.00100%$7,640.00$0.00
Variations subtotal$7,640.00$7,640.00$0.00$7,640.00$0.00
Total$275,640.00$244,820.00$30,820.00$275,640.00$0.00

This is a payment claim made under the Building and Construction Industry Security of Payment Act 1999 (NSW).

Claim summary

Contract sum
$268,000.00
Accepted Variations
$7,640.00
Revised contract sum
$275,640.00
Work completed to date (100%)
$275,640.00
Less work previously claimed
-$244,820.00
Value of work this claim
$30,820.00
Less Retention held this claim
-$1,159.00
Add Retention released at practical completion
$6,700.00
Amount of this claim, ex GST
$36,361.00
GST (10%)
$3,636.10
Amount due, inc GST
$39,997.10

Certified $36,361.00 ex GST, $39,997.10 inc GST, in full

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$13,400.00
Held before this claim
$12,241.00
Held after this claim
$6,700.00
Released at practical completion
50%, $6,700.00
Rest at the end of the defects period
50%, 11/09/2027
Practical completion
11/09/2026

Claim history

ClaimThis claimTo date
PC-10459-0125/05/2026, Approved$36,233.00$38,140.00
PC-10459-0225/06/2026, Approved$50,255.00$91,040.00
PC-10459-0324/07/2026, Approved$74,869.50$169,850.00
PC-10459-0425/08/2026, Approved$71,221.50$244,820.00
PC-10459-0525/09/2026, Approved$36,361.00$275,640.00

This claim is ex GST, after Retention. To date is work completed, before Retention.