RFIHeld onRaised byToRaisedDueAnsweredDays openStatus
Re F-201: A mezzanine was added over the Block D lab prep room. Confirm whether it needs its own coverage or is covered from below.Job 10458Fire services, Block D science buildingKate LindqvistHamish GreerFacilities manager13/10/202620/10/202611 days overdue-18Overdue
Re E-202: Bays 3 and 4 have a lower roof truss line. Confirm the mounting height for the high-bay fittings against the lighting layout.Job 10457Electrical services, Stage 2 warehouseKate LindqvistSam TeasdaleConstruction manager19/10/202626/10/20265 days overdue-12Overdue
The CHW riser from Level 7 to 9 is only reachable after hours. Confirm the access arrangement.Job 10434Leak repairs, CHW riser L4 to L9Priya NairErin CallowayBuilding manager23/10/202628/10/20263 days overdue-8Overdue
The isolator replacement needs a full-site shutdown. Which weekend suits?Job 10449Main switchboard isolator replacementSam OkaforDaniel FerreiraBuilding manager21/10/202628/10/20263 days overdue-10Overdue
Re M-401: The controls schematic puts the BMS controller in the Level 7 comms room. The comms room is fully allocated. Where does the controller go?Job 10456Mechanical services, Levels 3 to 8 fit-outRob HendryAngela PapadakisProject manager22/10/202629/10/20262 days overdue-9Overdue

Showing 1 to 5 of 5 RFIs