Average days to answer
4.1 days
Raised to answered, across answered RFIs
| RFI | Held on | Raised by | To | Raised | Due | Answered | Days open | Status |
|---|---|---|---|---|---|---|---|---|
| Re F-201: Confirm the shutdown date for tying the new fire panel into the Block D supply. | Project P-103Tallowood College, Block D science building | Kate Lindqvist | Hamish GreerFacilities manager | 09/10/2026 | 16/10/202615 days overdue | - | 22 | Overdue |
| Re F-201: A mezzanine was added over the Block D lab prep room. Confirm whether it needs its own coverage or is covered from below. | Job 10458Fire services, Block D science building | Kate Lindqvist | Hamish GreerFacilities manager | 13/10/2026 | 20/10/202611 days overdue | - | 18 | Overdue |
| Re E-202: Bays 3 and 4 have a lower roof truss line. Confirm the mounting height for the high-bay fittings against the lighting layout. | Job 10457Electrical services, Stage 2 warehouse | Kate Lindqvist | Sam TeasdaleConstruction manager | 19/10/2026 | 26/10/20265 days overdue | - | 12 | Overdue |
| Re A-201: Level 6 ceiling layout moved after the last issue. Confirm the current reflected ceiling plan is Rev D. | Project P-101Westmoor Tower, Levels 3 to 8 fit-out | Kate Lindqvist | Costa VargaSite manager | 20/10/2026 | 27/10/20264 days overdue | - | 11 | Overdue |
| The CHW riser from Level 7 to 9 is only reachable after hours. Confirm the access arrangement. | Job 10434Leak repairs, CHW riser L4 to L9 | Priya Nair | Erin CallowayBuilding manager | 23/10/2026 | 28/10/20263 days overdue | - | 8 | Overdue |
| The isolator replacement needs a full-site shutdown. Which weekend suits? | Job 10449Main switchboard isolator replacement | Sam Okafor | Daniel FerreiraBuilding manager | 21/10/2026 | 28/10/20263 days overdue | - | 10 | Overdue |
| Confirm spare capacity at the Level 13 distribution board for the new amenities load. | Tender T-2124Westmoor Tower Level 13 amenities, electrical | Sam Okafor | Angela PapadakisProject manager | 21/10/2026 | 28/10/20263 days overdue | - | 10 | Overdue |
| Re M-401: The controls schematic puts the BMS controller in the Level 7 comms room. The comms room is fully allocated. Where does the controller go? | Job 10456Mechanical services, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 22/10/2026 | 29/10/20262 days overdue | - | 9 | Overdue |
| The BMS points list appears in the specification but not on the drawings. Confirm whether BMS controls are in our package. | Tender T-2128Southbank Arcade Level 2 conversion, mechanical | Rob Hendry | Tess MoriartyAsset manager | 26/10/2026 | 30/10/20261 day overdue | - | 5 | Overdue |
Showing 1 to 9 of 9 RFIs