Average days to answer
4.1 days
Raised to answered, across answered RFIs
| RFI | Held on | Raised by | To | Raised | Due | Answered | Days open | Status |
|---|---|---|---|---|---|---|---|---|
| Re F-201: Confirm the shutdown date for tying the new fire panel into the Block D supply. | Project P-103Tallowood College, Block D science building | Kate Lindqvist | Hamish GreerFacilities manager | 09/10/2026 | 16/10/202615 days overdue | - | 22 | Overdue |
| Re F-201: A mezzanine was added over the Block D lab prep room. Confirm whether it needs its own coverage or is covered from below. | Job 10458Fire services, Block D science building | Kate Lindqvist | Hamish GreerFacilities manager | 13/10/2026 | 20/10/202611 days overdue | - | 18 | Overdue |
| Re E-202: Bays 3 and 4 have a lower roof truss line. Confirm the mounting height for the high-bay fittings against the lighting layout. | Job 10457Electrical services, Stage 2 warehouse | Kate Lindqvist | Sam TeasdaleConstruction manager | 19/10/2026 | 26/10/20265 days overdue | - | 12 | Overdue |
| Re A-201: Level 6 ceiling layout moved after the last issue. Confirm the current reflected ceiling plan is Rev D. | Project P-101Westmoor Tower, Levels 3 to 8 fit-out | Kate Lindqvist | Costa VargaSite manager | 20/10/2026 | 27/10/20264 days overdue | - | 11 | Overdue |
| The CHW riser from Level 7 to 9 is only reachable after hours. Confirm the access arrangement. | Job 10434Leak repairs, CHW riser L4 to L9 | Priya Nair | Erin CallowayBuilding manager | 23/10/2026 | 28/10/20263 days overdue | - | 8 | Overdue |
| The isolator replacement needs a full-site shutdown. Which weekend suits? | Job 10449Main switchboard isolator replacement | Sam Okafor | Daniel FerreiraBuilding manager | 21/10/2026 | 28/10/20263 days overdue | - | 10 | Overdue |
| Confirm spare capacity at the Level 13 distribution board for the new amenities load. | Tender T-2124Westmoor Tower Level 13 amenities, electrical | Sam Okafor | Angela PapadakisProject manager | 21/10/2026 | 28/10/20263 days overdue | - | 10 | Overdue |
| Re M-401: The controls schematic puts the BMS controller in the Level 7 comms room. The comms room is fully allocated. Where does the controller go? | Job 10456Mechanical services, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 22/10/2026 | 29/10/20262 days overdue | - | 9 | Overdue |
| The BMS points list appears in the specification but not on the drawings. Confirm whether BMS controls are in our package. | Tender T-2128Southbank Arcade Level 2 conversion, mechanical | Rob Hendry | Tess MoriartyAsset manager | 26/10/2026 | 30/10/20261 day overdue | - | 5 | Overdue |
| Chiller 1 needs a four-hour isolation to swap the contactor. Which window suits the facility? | Job 10431CH1 C2 contactor and overload replacement | Liam Cartwright | Dean WhitlockFacilities manager | 28/10/2026 | 31/10/2026 | - | 3 | Open |
| Confirm the Stage 2 practical completion date and the access date for electrical fit-off. | Project P-102Brightwater Logistics Hub, Stage 2 | Sam Okafor | Holly BrennanSite manager | 25/10/2026 | 01/11/2026 | - | 6 | Open |
| Confirm the date and street permit for the crane lift of the Level 2 condenser. | Project P-105Ironbark Offices, Level 2 tenancy | Kate Lindqvist | Pia LindgrenSite manager | 26/10/2026 | 02/11/2026 | - | 5 | Open |
| Confirm the BMS network firmware version before the controllers are ordered. | Job 10453BMS controller replacement, AHU 6 to 9 | Rob Hendry | Nadia KowalczykDevelopment manager | 27/10/2026 | 03/11/2026 | - | 4 | Open |
| Re M-202: Confirm the fire damper positions where ductwork crosses the Level 4 service shaft wall, against the fire engineer's markup. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Sam Okafor | Costa VargaSite manager | 28/10/2026 | 04/11/2026 | - | 3 | Open |
| Re M-301: The terrace plan shows the condenser against the parapet. Confirm the clearance to the parapet and the plant screen. | Job 10460Package unit replacement, Level 2 tenancy | Kate Lindqvist | Pia LindgrenSite manager | 29/10/2026 | 05/11/2026 | - | 2 | Open |
| Core drilling for the risers needs after-hours work. Confirm the permitted hours and the notice period. | Project P-101Westmoor Tower, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 29/10/2026 | 05/11/2026 | - | 2 | Open |
| Re M-101: The plant room moved to the roof. Does the builder provide the crane and the lift permit? | Tender T-2128Southbank Arcade Level 2 conversion, mechanical | Rob Hendry | Tess MoriartyAsset manager | 29/10/2026 | 05/11/2026 | - | 2 | Open |
| The reissued fire engineering report moves the smoke zone boundaries. Confirm the zones the detection layout should follow. | Tender T-2131Tallowood College Block G refurbishment, fire | Kate Lindqvist | Hamish GreerFacilities manager | 30/10/2026 | 06/11/2026 | - | 1 | Open |
| The landlord has an approved VAV box list. Confirm we price from it. | Tender T-2133Parkside Commerce Centre Level 9 fit-out, mechanical | Rob Hendry | Nadia KowalczykDevelopment manager | 31/10/2026 | 07/11/2026 | - | 0 | Open |
| The fire damper schedule is missing from the tender pack. Please issue it.Answer: Schedule issued by email. | Tender T-2101Westmoor Tower, Levels 3 to 8 mechanical services | Rob Hendry | Angela PapadakisProject manager | 06/05/2026 | 13/05/2026 | 09/05/2026 | 3 | Answered |
| Confirm approved slab penetration locations on Level 3 for the new risers.Answer: Approved at gridlines B/4 and D/4. | Project P-104Parkside Commerce Centre, Levels 1 to 4 refurbishment | Rob Hendry | Nadia KowalczykDevelopment manager | 03/06/2026 | 10/06/2026 | 07/06/2026 | 4 | Answered |
| Confirm whether the switchgear is builder supplied or ours.Answer: Ours, supplied and installed. | Tender T-2103Brightwater Logistics Hub Stage 2, electrical services | Sam Okafor | Sam TeasdaleConstruction manager | 15/06/2026 | 22/06/2026 | 19/06/2026 | 4 | Answered |
| Access to the Level 2 riser is behind a fixed panel. Confirm who removes it and when.Answer: Builder removes the panel before ductwork starts. | Job 10459Mechanical services refurbishment, Levels 1 to 4 | Rob Hendry | Nadia KowalczykDevelopment manager | 03/07/2026 | 10/07/2026 | 05/07/2026 | 2 | Answered |
| Re E-301: The main switchboard is 2.4 m wide. The door opening on the architectural plan is 2.1 m. Confirm the access path for delivery.Answer: Door widened to 2.5 m. Architectural Rev C to follow. | Job 10457Electrical services, Stage 2 warehouse | Sam Okafor | Holly BrennanSite manager | 01/09/2026 | 08/09/2026 | 06/09/2026 | 5 | Answered |
| Confirm the date for the practical completion inspection and who attends for the mechanical works.Answer: Booked for the following Tuesday. Attend with the commissioning engineer. | Project P-104Parkside Commerce Centre, Levels 1 to 4 refurbishment | Kate Lindqvist | Nadia KowalczykDevelopment manager | 01/09/2026 | 08/09/2026 | 04/09/2026 | 3 | Answered |
Showing 1 to 25 of 40 RFIs. 19 on Jobs, 10 on Projects, 11 on Tenders