Work

RFIs

MS
RFIHeld onRaised byToRaisedDueAnsweredDays openStatus
Confirm spare capacity at the Level 13 distribution board for the new amenities load.Tender T-2124Westmoor Tower Level 13 amenities, electricalSam OkaforAngela PapadakisProject manager21/10/202628/10/20263 days overdue-10Overdue
The BMS points list appears in the specification but not on the drawings. Confirm whether BMS controls are in our package.Tender T-2128Southbank Arcade Level 2 conversion, mechanicalRob HendryTess MoriartyAsset manager26/10/202630/10/20261 day overdue-5Overdue
Re M-101: The plant room moved to the roof. Does the builder provide the crane and the lift permit?Tender T-2128Southbank Arcade Level 2 conversion, mechanicalRob HendryTess MoriartyAsset manager29/10/202605/11/2026-2Open
The reissued fire engineering report moves the smoke zone boundaries. Confirm the zones the detection layout should follow.Tender T-2131Tallowood College Block G refurbishment, fireKate LindqvistHamish GreerFacilities manager30/10/202606/11/2026-1Open
The landlord has an approved VAV box list. Confirm we price from it.Tender T-2133Parkside Commerce Centre Level 9 fit-out, mechanicalRob HendryNadia KowalczykDevelopment manager31/10/202607/11/2026-0Open
The fire damper schedule is missing from the tender pack. Please issue it.Answer: Schedule issued by email.Tender T-2101Westmoor Tower, Levels 3 to 8 mechanical servicesRob HendryAngela PapadakisProject manager06/05/202613/05/202609/05/20263Answered
Confirm whether the switchgear is builder supplied or ours.Answer: Ours, supplied and installed.Tender T-2103Brightwater Logistics Hub Stage 2, electrical servicesSam OkaforSam TeasdaleConstruction manager15/06/202622/06/202619/06/20264Answered
Re F-101: Confirm the booster location on the north wall against the revised plan.Answer: North wall, 2 m east of the stair.Tender T-2112Northgate Hospital Block C plant room, fireKate LindqvistVictor AmoahPlant supervisor28/09/202605/10/202603/10/20265Answered
Confirm the design ventilation rate for the car park.Answer: 6 air changes per hour, minimum.Tender T-2113Southbank car park, mechanical ventilation upgradeKate LindqvistTess MoriartyAsset manager01/10/202608/10/202605/10/20264Answered
Confirm whether disposal of the existing luminaires is in our scope.Answer: Builder removes and disposes of the existing luminaires.Tender T-2127Kestrel Place Level 4 lighting upgradeSam OkaforJess ThornburyBuilding manager24/10/202629/10/202627/10/20263Answered
The revised ceiling layout on Level 14 changes the diffuser count. Confirm the count.Answer: 46 diffusers.Tender T-2123Ironbark Barangaroo tenancy fit-out, HVACRob HendryLuke ArmstrongContracts administrator27/10/202603/11/202629/10/20262Answered

Showing 1 to 11 of 11 RFIs