Work

RFIs

MS
RFIHeld onRaised byToRaisedDueAnsweredDays openStatus
Confirm whether the Level 1 laboratories are classified as containment areas for the detection design.Answer: Not containment. Standard detection applies.Project P-103Tallowood College, Block D science buildingSam OkaforRuby OkoroGrounds and maintenance lead11/09/202618/09/202616/09/20265Answered
Who signs off the defects list at practical completion?Answer: Nadia Kowalczyk signs off. Copy the facilities coordinator.Job 10459Mechanical services refurbishment, Levels 1 to 4Kate LindqvistNadia KowalczykDevelopment manager16/09/202623/09/202621/09/20265Answered
Re M-201: The structural beam at gridline C/5 clashes with the supply air riser. Can the riser be offset 300 mm east, or does the beam get a penetration?Answer: Offset the riser 300 mm east. Revised M-201 issued as Rev B.Job 10456Mechanical services, Levels 3 to 8 fit-outRob HendryAngela PapadakisProject manager17/09/202624/09/202621/09/20264Answered
Confirm the finished ceiling height over the Level 8 plant deck so the supply ductwork can be coordinated.Answer: 2700 mm AFFL.Project P-101Westmoor Tower, Levels 3 to 8 fit-outRob HendryAngela PapadakisProject manager25/09/202602/10/202630/09/20265Answered
Confirm the detector type inside the laboratory fume cupboard extract ducts.Answer: Duct-mounted smoke detectors, supplied by the mechanical contractor.Job 10458Fire services, Block D science buildingRob HendryRuby OkoroGrounds and maintenance lead26/09/202603/10/202601/10/20265Answered
Re A-401: Confirm the mezzanine floor load rating for the Stage 2 racking and the electrical plant above.Answer: 5 kPa distributed. Plant above to be on its own plinths.Project P-102Brightwater Logistics Hub, Stage 2Sam OkaforSam TeasdaleConstruction manager28/09/202605/10/202603/10/20265Answered
Re F-101: Confirm the booster location on the north wall against the revised plan.Answer: North wall, 2 m east of the stair.Tender T-2112Northgate Hospital Block C plant room, fireKate LindqvistVictor AmoahPlant supervisor28/09/202605/10/202603/10/20265Answered
Confirm the void depth above the Level 2 ceiling for the package unit ducting.Answer: 450 mm clear to the slab. Hangers by the builder.Job 10460Package unit replacement, Level 2 tenancySam OkaforLuke ArmstrongContracts administrator01/10/202608/10/202605/10/20264Answered
Confirm the design ventilation rate for the car park.Answer: 6 air changes per hour, minimum.Tender T-2113Southbank car park, mechanical ventilation upgradeKate LindqvistTess MoriartyAsset manager01/10/202608/10/202605/10/20264Answered
Where do the two EV charger circuits land in the car park, and who provides the trench to the first pit?Answer: Chargers at bay 1 and bay 8. Builder trenches to the first pit.Job 10457Electrical services, Stage 2 warehouseSam OkaforHolly BrennanSite manager05/10/202612/10/202609/10/20264Answered
The reflected ceiling plan shows 450 mm panels. The fan coil units need 600 mm to pull the coil. Confirm the panel size and who supplies the grid trim.Answer: Provide 600 x 600 panels. Ceiling contractor supplies the trim.Job 10456Mechanical services, Levels 3 to 8 fit-outSam OkaforCosta VargaSite manager11/10/202618/10/202616/10/20265Answered
Confirm the colour temperature for the high-bay LED upgrade, 4000 K or 5000 K.Answer: 4000 K.Job 10447Warehouse high-bay LED upgradeSienna WalshSam TeasdaleConstruction manager15/10/202622/10/202620/10/20265Answered
The drawing shows 60 data outlets. The tenancy schedule says 72. Which governs?Answer: 72 per the tenancy schedule. Drawing to be updated.Job 10438Level 3 fit-out power and dataSam OkaforAngela PapadakisProject manager17/10/202624/10/202622/10/20265Answered
Confirm whether disposal of the existing luminaires is in our scope.Answer: Builder removes and disposes of the existing luminaires.Tender T-2127Kestrel Place Level 4 lighting upgradeSam OkaforJess ThornburyBuilding manager24/10/202629/10/202627/10/20263Answered
The revised ceiling layout on Level 14 changes the diffuser count. Confirm the count.Answer: 46 diffusers.Tender T-2123Ironbark Barangaroo tenancy fit-out, HVACRob HendryLuke ArmstrongContracts administrator27/10/202603/11/202629/10/20262Answered

Showing 26 to 40 of 40 RFIs. 19 on Jobs, 10 on Projects, 11 on Tenders