Average days to answer
4.1 days
Raised to answered, across answered RFIs
| RFI | Held on | Raised by | To | Raised | Due | Answered | Days open | Status |
|---|---|---|---|---|---|---|---|---|
| Re F-201: A mezzanine was added over the Block D lab prep room. Confirm whether it needs its own coverage or is covered from below. | Job 10458Fire services, Block D science building | Kate Lindqvist | Hamish GreerFacilities manager | 13/10/2026 | 20/10/202611 days overdue | - | 18 | Overdue |
| Re E-202: Bays 3 and 4 have a lower roof truss line. Confirm the mounting height for the high-bay fittings against the lighting layout. | Job 10457Electrical services, Stage 2 warehouse | Kate Lindqvist | Sam TeasdaleConstruction manager | 19/10/2026 | 26/10/20265 days overdue | - | 12 | Overdue |
| The CHW riser from Level 7 to 9 is only reachable after hours. Confirm the access arrangement. | Job 10434Leak repairs, CHW riser L4 to L9 | Priya Nair | Erin CallowayBuilding manager | 23/10/2026 | 28/10/20263 days overdue | - | 8 | Overdue |
| The isolator replacement needs a full-site shutdown. Which weekend suits? | Job 10449Main switchboard isolator replacement | Sam Okafor | Daniel FerreiraBuilding manager | 21/10/2026 | 28/10/20263 days overdue | - | 10 | Overdue |
| Re M-401: The controls schematic puts the BMS controller in the Level 7 comms room. The comms room is fully allocated. Where does the controller go? | Job 10456Mechanical services, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 22/10/2026 | 29/10/20262 days overdue | - | 9 | Overdue |
| Chiller 1 needs a four-hour isolation to swap the contactor. Which window suits the facility? | Job 10431CH1 C2 contactor and overload replacement | Liam Cartwright | Dean WhitlockFacilities manager | 28/10/2026 | 31/10/2026 | - | 3 | Open |
| Confirm the BMS network firmware version before the controllers are ordered. | Job 10453BMS controller replacement, AHU 6 to 9 | Rob Hendry | Nadia KowalczykDevelopment manager | 27/10/2026 | 03/11/2026 | - | 4 | Open |
| Re M-202: Confirm the fire damper positions where ductwork crosses the Level 4 service shaft wall, against the fire engineer's markup. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Sam Okafor | Costa VargaSite manager | 28/10/2026 | 04/11/2026 | - | 3 | Open |
| Re M-301: The terrace plan shows the condenser against the parapet. Confirm the clearance to the parapet and the plant screen. | Job 10460Package unit replacement, Level 2 tenancy | Kate Lindqvist | Pia LindgrenSite manager | 29/10/2026 | 05/11/2026 | - | 2 | Open |
Showing 1 to 9 of 9 RFIs