RFIHeld onRaised byToRaisedDueAnsweredDays openStatus
Confirm approved slab penetration locations on Level 3 for the new risers.Answer: Approved at gridlines B/4 and D/4.Project P-104Parkside Commerce Centre, Levels 1 to 4 refurbishmentRob HendryNadia KowalczykDevelopment manager03/06/202610/06/202607/06/20264Answered
Confirm the date for the practical completion inspection and who attends for the mechanical works.Answer: Booked for the following Tuesday. Attend with the commissioning engineer.Project P-104Parkside Commerce Centre, Levels 1 to 4 refurbishmentKate LindqvistNadia KowalczykDevelopment manager01/09/202608/09/202604/09/20263Answered
Confirm whether the Level 1 laboratories are classified as containment areas for the detection design.Answer: Not containment. Standard detection applies.Project P-103Tallowood College, Block D science buildingSam OkaforRuby OkoroGrounds and maintenance lead11/09/202618/09/202616/09/20265Answered
Confirm the finished ceiling height over the Level 8 plant deck so the supply ductwork can be coordinated.Answer: 2700 mm AFFL.Project P-101Westmoor Tower, Levels 3 to 8 fit-outRob HendryAngela PapadakisProject manager25/09/202602/10/202630/09/20265Answered
Re A-401: Confirm the mezzanine floor load rating for the Stage 2 racking and the electrical plant above.Answer: 5 kPa distributed. Plant above to be on its own plinths.Project P-102Brightwater Logistics Hub, Stage 2Sam OkaforSam TeasdaleConstruction manager28/09/202605/10/202603/10/20265Answered

Showing 1 to 5 of 5 RFIs