Money

Progress Claims

MS

Progress Claims

Progress Claim PC-10457-04

Draft

Job 10457, Electrical services, Stage 2 warehouse

Brightwater Builders, attention Sam Teasdale. Subcontract BB-2026-118. Brightwater Logistics Hub, Stage 2, 14 Industry Dr, Eagle Farm QLD 4009

Period ending
23/10/2026
Submitted
Not yet
Payment schedule due
-
Payment due
-

Claim schedule

Enter each line's percent complete to date. Everything else works itself out.

Previously claimedThis claimComplete to date
ItemDescriptionValue%$%$%$Balance
Contract works
1Preliminaries$12,500.0085%$10,625.005%$625.00%$11,250.00$1,250.00
2Consumer mains and main switchboard$46,800.0090%$42,120.0010%$4,680.00%$46,800.00$0.00
3Distribution boards$28,400.0075%$21,300.0025%$7,100.00%$28,400.00$0.00
4Cable tray and containment$39,200.0085%$33,320.0015%$5,880.00%$39,200.00$0.00
5Sub-mains and final subcircuits$64,300.0055%$35,365.0025%$16,075.00%$51,440.00$12,860.00
6High-bay and external lighting$71,600.0020%$14,320.0030%$21,480.00%$35,800.00$35,800.00
7Emergency and exit lighting$18,900.000%$0.0020%$3,780.00%$3,780.00$15,120.00
8Data and security rough-in$17,600.000%$0.0030%$5,280.00%$5,280.00$12,320.00
9Testing, commissioning and certification$13,200.000%$0.000%$0.00%$0.00$13,200.00
Contract works subtotal$312,500.00$157,050.00$64,900.00$221,950.00$90,550.00
Accepted Variations
V01EV charger circuits, car park$14,280.0040%$5,712.0060%$8,568.00%$14,280.00$0.00
Variations subtotal$14,280.00$5,712.00$8,568.00$14,280.00$0.00
Total$326,780.00$162,762.00$73,468.00$236,230.00$90,550.00

This is a payment claim made under the Building Industry Fairness (Security of Payment) Act 2017 (Qld). This claim requests payment of the claimed amount.

Claim summary

Contract sum
$312,500.00
Accepted Variations
$14,280.00
Revised contract sum
$326,780.00
Work completed to date (72.3%)
$236,230.00
Less work previously claimed
-$162,762.00
Value of work this claim
$73,468.00
Less Retention held this claim
-$3,673.40
Amount of this claim, ex GST
$69,794.60
GST (10%)
$6,979.46
Amount due, inc GST
$76,774.06

Retention

Terms
5% of the value of work to date, capped at 5% of the contract sum
Cap
$15,625.00
Held before this claim
$8,138.10
Held after this claim
$11,811.50
Released at practical completion
50%, $5,905.75
Rest at the end of the defects period
50%, 12 months after practical completion
Practical completion
Not reached

Claim history

ClaimThis claimTo date
PC-10457-0124/07/2026, Approved$26,001.50$27,370.00
PC-10457-0225/08/2026, Submitted$57,394.25$87,785.00
PC-10457-0325/09/2026, Submitted$71,228.15$162,762.00
PC-10457-0423/10/2026, Draft$69,794.60$236,230.00

This claim is ex GST, after Retention. To date is work completed, before Retention.