Average days to answer
4.1 days
Raised to answered, across answered RFIs
| RFI | Held on | Raised by | To | Raised | Due | Answered | Days open | Status |
|---|---|---|---|---|---|---|---|---|
| Re F-201: A mezzanine was added over the Block D lab prep room. Confirm whether it needs its own coverage or is covered from below. | Job 10458Fire services, Block D science building | Kate Lindqvist | Hamish GreerFacilities manager | 13/10/2026 | 20/10/202611 days overdue | - | 18 | Overdue |
| Re E-202: Bays 3 and 4 have a lower roof truss line. Confirm the mounting height for the high-bay fittings against the lighting layout. | Job 10457Electrical services, Stage 2 warehouse | Kate Lindqvist | Sam TeasdaleConstruction manager | 19/10/2026 | 26/10/20265 days overdue | - | 12 | Overdue |
| The CHW riser from Level 7 to 9 is only reachable after hours. Confirm the access arrangement. | Job 10434Leak repairs, CHW riser L4 to L9 | Priya Nair | Erin CallowayBuilding manager | 23/10/2026 | 28/10/20263 days overdue | - | 8 | Overdue |
| The isolator replacement needs a full-site shutdown. Which weekend suits? | Job 10449Main switchboard isolator replacement | Sam Okafor | Daniel FerreiraBuilding manager | 21/10/2026 | 28/10/20263 days overdue | - | 10 | Overdue |
| Re M-401: The controls schematic puts the BMS controller in the Level 7 comms room. The comms room is fully allocated. Where does the controller go? | Job 10456Mechanical services, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 22/10/2026 | 29/10/20262 days overdue | - | 9 | Overdue |
| Chiller 1 needs a four-hour isolation to swap the contactor. Which window suits the facility? | Job 10431CH1 C2 contactor and overload replacement | Liam Cartwright | Dean WhitlockFacilities manager | 28/10/2026 | 31/10/2026 | - | 3 | Open |
| Confirm the BMS network firmware version before the controllers are ordered. | Job 10453BMS controller replacement, AHU 6 to 9 | Rob Hendry | Nadia KowalczykDevelopment manager | 27/10/2026 | 03/11/2026 | - | 4 | Open |
| Re M-202: Confirm the fire damper positions where ductwork crosses the Level 4 service shaft wall, against the fire engineer's markup. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Sam Okafor | Costa VargaSite manager | 28/10/2026 | 04/11/2026 | - | 3 | Open |
| Re M-301: The terrace plan shows the condenser against the parapet. Confirm the clearance to the parapet and the plant screen. | Job 10460Package unit replacement, Level 2 tenancy | Kate Lindqvist | Pia LindgrenSite manager | 29/10/2026 | 05/11/2026 | - | 2 | Open |
| Access to the Level 2 riser is behind a fixed panel. Confirm who removes it and when.Answer: Builder removes the panel before ductwork starts. | Job 10459Mechanical services refurbishment, Levels 1 to 4 | Rob Hendry | Nadia KowalczykDevelopment manager | 03/07/2026 | 10/07/2026 | 05/07/2026 | 2 | Answered |
| Re E-301: The main switchboard is 2.4 m wide. The door opening on the architectural plan is 2.1 m. Confirm the access path for delivery.Answer: Door widened to 2.5 m. Architectural Rev C to follow. | Job 10457Electrical services, Stage 2 warehouse | Sam Okafor | Holly BrennanSite manager | 01/09/2026 | 08/09/2026 | 06/09/2026 | 5 | Answered |
| Who signs off the defects list at practical completion?Answer: Nadia Kowalczyk signs off. Copy the facilities coordinator. | Job 10459Mechanical services refurbishment, Levels 1 to 4 | Kate Lindqvist | Nadia KowalczykDevelopment manager | 16/09/2026 | 23/09/2026 | 21/09/2026 | 5 | Answered |
| Re M-201: The structural beam at gridline C/5 clashes with the supply air riser. Can the riser be offset 300 mm east, or does the beam get a penetration?Answer: Offset the riser 300 mm east. Revised M-201 issued as Rev B. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 17/09/2026 | 24/09/2026 | 21/09/2026 | 4 | Answered |
| Confirm the detector type inside the laboratory fume cupboard extract ducts.Answer: Duct-mounted smoke detectors, supplied by the mechanical contractor. | Job 10458Fire services, Block D science building | Rob Hendry | Ruby OkoroGrounds and maintenance lead | 26/09/2026 | 03/10/2026 | 01/10/2026 | 5 | Answered |
| Confirm the void depth above the Level 2 ceiling for the package unit ducting.Answer: 450 mm clear to the slab. Hangers by the builder. | Job 10460Package unit replacement, Level 2 tenancy | Sam Okafor | Luke ArmstrongContracts administrator | 01/10/2026 | 08/10/2026 | 05/10/2026 | 4 | Answered |
| Where do the two EV charger circuits land in the car park, and who provides the trench to the first pit?Answer: Chargers at bay 1 and bay 8. Builder trenches to the first pit. | Job 10457Electrical services, Stage 2 warehouse | Sam Okafor | Holly BrennanSite manager | 05/10/2026 | 12/10/2026 | 09/10/2026 | 4 | Answered |
| The reflected ceiling plan shows 450 mm panels. The fan coil units need 600 mm to pull the coil. Confirm the panel size and who supplies the grid trim.Answer: Provide 600 x 600 panels. Ceiling contractor supplies the trim. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Sam Okafor | Costa VargaSite manager | 11/10/2026 | 18/10/2026 | 16/10/2026 | 5 | Answered |
| Confirm the colour temperature for the high-bay LED upgrade, 4000 K or 5000 K.Answer: 4000 K. | Job 10447Warehouse high-bay LED upgrade | Sienna Walsh | Sam TeasdaleConstruction manager | 15/10/2026 | 22/10/2026 | 20/10/2026 | 5 | Answered |
| The drawing shows 60 data outlets. The tenancy schedule says 72. Which governs?Answer: 72 per the tenancy schedule. Drawing to be updated. | Job 10438Level 3 fit-out power and data | Sam Okafor | Angela PapadakisProject manager | 17/10/2026 | 24/10/2026 | 22/10/2026 | 5 | Answered |
Showing 1 to 19 of 19 RFIs