Average days to answer
4.1 days
Raised to answered, across answered RFIs
| RFI | Held on | Raised by | To | Raised | Due | Answered | Days open | Status |
|---|---|---|---|---|---|---|---|---|
| The fire damper schedule is missing from the tender pack. Please issue it.Answer: Schedule issued by email. | Tender T-2101Westmoor Tower, Levels 3 to 8 mechanical services | Rob Hendry | Angela PapadakisProject manager | 06/05/2026 | 13/05/2026 | 09/05/2026 | 3 | Answered |
| Confirm approved slab penetration locations on Level 3 for the new risers.Answer: Approved at gridlines B/4 and D/4. | Project P-104Parkside Commerce Centre, Levels 1 to 4 refurbishment | Rob Hendry | Nadia KowalczykDevelopment manager | 03/06/2026 | 10/06/2026 | 07/06/2026 | 4 | Answered |
| Confirm whether the switchgear is builder supplied or ours.Answer: Ours, supplied and installed. | Tender T-2103Brightwater Logistics Hub Stage 2, electrical services | Sam Okafor | Sam TeasdaleConstruction manager | 15/06/2026 | 22/06/2026 | 19/06/2026 | 4 | Answered |
| Access to the Level 2 riser is behind a fixed panel. Confirm who removes it and when.Answer: Builder removes the panel before ductwork starts. | Job 10459Mechanical services refurbishment, Levels 1 to 4 | Rob Hendry | Nadia KowalczykDevelopment manager | 03/07/2026 | 10/07/2026 | 05/07/2026 | 2 | Answered |
| Re E-301: The main switchboard is 2.4 m wide. The door opening on the architectural plan is 2.1 m. Confirm the access path for delivery.Answer: Door widened to 2.5 m. Architectural Rev C to follow. | Job 10457Electrical services, Stage 2 warehouse | Sam Okafor | Holly BrennanSite manager | 01/09/2026 | 08/09/2026 | 06/09/2026 | 5 | Answered |
| Confirm the date for the practical completion inspection and who attends for the mechanical works.Answer: Booked for the following Tuesday. Attend with the commissioning engineer. | Project P-104Parkside Commerce Centre, Levels 1 to 4 refurbishment | Kate Lindqvist | Nadia KowalczykDevelopment manager | 01/09/2026 | 08/09/2026 | 04/09/2026 | 3 | Answered |
| Confirm whether the Level 1 laboratories are classified as containment areas for the detection design.Answer: Not containment. Standard detection applies. | Project P-103Tallowood College, Block D science building | Sam Okafor | Ruby OkoroGrounds and maintenance lead | 11/09/2026 | 18/09/2026 | 16/09/2026 | 5 | Answered |
| Who signs off the defects list at practical completion?Answer: Nadia Kowalczyk signs off. Copy the facilities coordinator. | Job 10459Mechanical services refurbishment, Levels 1 to 4 | Kate Lindqvist | Nadia KowalczykDevelopment manager | 16/09/2026 | 23/09/2026 | 21/09/2026 | 5 | Answered |
| Re M-201: The structural beam at gridline C/5 clashes with the supply air riser. Can the riser be offset 300 mm east, or does the beam get a penetration?Answer: Offset the riser 300 mm east. Revised M-201 issued as Rev B. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 17/09/2026 | 24/09/2026 | 21/09/2026 | 4 | Answered |
| Confirm the finished ceiling height over the Level 8 plant deck so the supply ductwork can be coordinated.Answer: 2700 mm AFFL. | Project P-101Westmoor Tower, Levels 3 to 8 fit-out | Rob Hendry | Angela PapadakisProject manager | 25/09/2026 | 02/10/2026 | 30/09/2026 | 5 | Answered |
| Confirm the detector type inside the laboratory fume cupboard extract ducts.Answer: Duct-mounted smoke detectors, supplied by the mechanical contractor. | Job 10458Fire services, Block D science building | Rob Hendry | Ruby OkoroGrounds and maintenance lead | 26/09/2026 | 03/10/2026 | 01/10/2026 | 5 | Answered |
| Re A-401: Confirm the mezzanine floor load rating for the Stage 2 racking and the electrical plant above.Answer: 5 kPa distributed. Plant above to be on its own plinths. | Project P-102Brightwater Logistics Hub, Stage 2 | Sam Okafor | Sam TeasdaleConstruction manager | 28/09/2026 | 05/10/2026 | 03/10/2026 | 5 | Answered |
| Re F-101: Confirm the booster location on the north wall against the revised plan.Answer: North wall, 2 m east of the stair. | Tender T-2112Northgate Hospital Block C plant room, fire | Kate Lindqvist | Victor AmoahPlant supervisor | 28/09/2026 | 05/10/2026 | 03/10/2026 | 5 | Answered |
| Confirm the void depth above the Level 2 ceiling for the package unit ducting.Answer: 450 mm clear to the slab. Hangers by the builder. | Job 10460Package unit replacement, Level 2 tenancy | Sam Okafor | Luke ArmstrongContracts administrator | 01/10/2026 | 08/10/2026 | 05/10/2026 | 4 | Answered |
| Confirm the design ventilation rate for the car park.Answer: 6 air changes per hour, minimum. | Tender T-2113Southbank car park, mechanical ventilation upgrade | Kate Lindqvist | Tess MoriartyAsset manager | 01/10/2026 | 08/10/2026 | 05/10/2026 | 4 | Answered |
| Where do the two EV charger circuits land in the car park, and who provides the trench to the first pit?Answer: Chargers at bay 1 and bay 8. Builder trenches to the first pit. | Job 10457Electrical services, Stage 2 warehouse | Sam Okafor | Holly BrennanSite manager | 05/10/2026 | 12/10/2026 | 09/10/2026 | 4 | Answered |
| The reflected ceiling plan shows 450 mm panels. The fan coil units need 600 mm to pull the coil. Confirm the panel size and who supplies the grid trim.Answer: Provide 600 x 600 panels. Ceiling contractor supplies the trim. | Job 10456Mechanical services, Levels 3 to 8 fit-out | Sam Okafor | Costa VargaSite manager | 11/10/2026 | 18/10/2026 | 16/10/2026 | 5 | Answered |
| Confirm the colour temperature for the high-bay LED upgrade, 4000 K or 5000 K.Answer: 4000 K. | Job 10447Warehouse high-bay LED upgrade | Sienna Walsh | Sam TeasdaleConstruction manager | 15/10/2026 | 22/10/2026 | 20/10/2026 | 5 | Answered |
| The drawing shows 60 data outlets. The tenancy schedule says 72. Which governs?Answer: 72 per the tenancy schedule. Drawing to be updated. | Job 10438Level 3 fit-out power and data | Sam Okafor | Angela PapadakisProject manager | 17/10/2026 | 24/10/2026 | 22/10/2026 | 5 | Answered |
| Confirm whether disposal of the existing luminaires is in our scope.Answer: Builder removes and disposes of the existing luminaires. | Tender T-2127Kestrel Place Level 4 lighting upgrade | Sam Okafor | Jess ThornburyBuilding manager | 24/10/2026 | 29/10/2026 | 27/10/2026 | 3 | Answered |
| The revised ceiling layout on Level 14 changes the diffuser count. Confirm the count.Answer: 46 diffusers. | Tender T-2123Ironbark Barangaroo tenancy fit-out, HVAC | Rob Hendry | Luke ArmstrongContracts administrator | 27/10/2026 | 03/11/2026 | 29/10/2026 | 2 | Answered |
Showing 1 to 21 of 21 RFIs