RFIHeld onRaised byToRaisedDueAnsweredDays openStatus
Re F-201: A mezzanine was added over the Block D lab prep room. Confirm whether it needs its own coverage or is covered from below.Job 10458Fire services, Block D science buildingKate LindqvistHamish GreerFacilities manager13/10/202620/10/202611 days overdue-18Overdue
Re E-202: Bays 3 and 4 have a lower roof truss line. Confirm the mounting height for the high-bay fittings against the lighting layout.Job 10457Electrical services, Stage 2 warehouseKate LindqvistSam TeasdaleConstruction manager19/10/202626/10/20265 days overdue-12Overdue
The CHW riser from Level 7 to 9 is only reachable after hours. Confirm the access arrangement.Job 10434Leak repairs, CHW riser L4 to L9Priya NairErin CallowayBuilding manager23/10/202628/10/20263 days overdue-8Overdue
The isolator replacement needs a full-site shutdown. Which weekend suits?Job 10449Main switchboard isolator replacementSam OkaforDaniel FerreiraBuilding manager21/10/202628/10/20263 days overdue-10Overdue
Re M-401: The controls schematic puts the BMS controller in the Level 7 comms room. The comms room is fully allocated. Where does the controller go?Job 10456Mechanical services, Levels 3 to 8 fit-outRob HendryAngela PapadakisProject manager22/10/202629/10/20262 days overdue-9Overdue
Chiller 1 needs a four-hour isolation to swap the contactor. Which window suits the facility?Job 10431CH1 C2 contactor and overload replacementLiam CartwrightDean WhitlockFacilities manager28/10/202631/10/2026-3Open
Confirm the BMS network firmware version before the controllers are ordered.Job 10453BMS controller replacement, AHU 6 to 9Rob HendryNadia KowalczykDevelopment manager27/10/202603/11/2026-4Open
Re M-202: Confirm the fire damper positions where ductwork crosses the Level 4 service shaft wall, against the fire engineer's markup.Job 10456Mechanical services, Levels 3 to 8 fit-outSam OkaforCosta VargaSite manager28/10/202604/11/2026-3Open
Re M-301: The terrace plan shows the condenser against the parapet. Confirm the clearance to the parapet and the plant screen.Job 10460Package unit replacement, Level 2 tenancyKate LindqvistPia LindgrenSite manager29/10/202605/11/2026-2Open
Access to the Level 2 riser is behind a fixed panel. Confirm who removes it and when.Answer: Builder removes the panel before ductwork starts.Job 10459Mechanical services refurbishment, Levels 1 to 4Rob HendryNadia KowalczykDevelopment manager03/07/202610/07/202605/07/20262Answered
Re E-301: The main switchboard is 2.4 m wide. The door opening on the architectural plan is 2.1 m. Confirm the access path for delivery.Answer: Door widened to 2.5 m. Architectural Rev C to follow.Job 10457Electrical services, Stage 2 warehouseSam OkaforHolly BrennanSite manager01/09/202608/09/202606/09/20265Answered
Who signs off the defects list at practical completion?Answer: Nadia Kowalczyk signs off. Copy the facilities coordinator.Job 10459Mechanical services refurbishment, Levels 1 to 4Kate LindqvistNadia KowalczykDevelopment manager16/09/202623/09/202621/09/20265Answered
Re M-201: The structural beam at gridline C/5 clashes with the supply air riser. Can the riser be offset 300 mm east, or does the beam get a penetration?Answer: Offset the riser 300 mm east. Revised M-201 issued as Rev B.Job 10456Mechanical services, Levels 3 to 8 fit-outRob HendryAngela PapadakisProject manager17/09/202624/09/202621/09/20264Answered
Confirm the detector type inside the laboratory fume cupboard extract ducts.Answer: Duct-mounted smoke detectors, supplied by the mechanical contractor.Job 10458Fire services, Block D science buildingRob HendryRuby OkoroGrounds and maintenance lead26/09/202603/10/202601/10/20265Answered
Confirm the void depth above the Level 2 ceiling for the package unit ducting.Answer: 450 mm clear to the slab. Hangers by the builder.Job 10460Package unit replacement, Level 2 tenancySam OkaforLuke ArmstrongContracts administrator01/10/202608/10/202605/10/20264Answered
Where do the two EV charger circuits land in the car park, and who provides the trench to the first pit?Answer: Chargers at bay 1 and bay 8. Builder trenches to the first pit.Job 10457Electrical services, Stage 2 warehouseSam OkaforHolly BrennanSite manager05/10/202612/10/202609/10/20264Answered
The reflected ceiling plan shows 450 mm panels. The fan coil units need 600 mm to pull the coil. Confirm the panel size and who supplies the grid trim.Answer: Provide 600 x 600 panels. Ceiling contractor supplies the trim.Job 10456Mechanical services, Levels 3 to 8 fit-outSam OkaforCosta VargaSite manager11/10/202618/10/202616/10/20265Answered
Confirm the colour temperature for the high-bay LED upgrade, 4000 K or 5000 K.Answer: 4000 K.Job 10447Warehouse high-bay LED upgradeSienna WalshSam TeasdaleConstruction manager15/10/202622/10/202620/10/20265Answered
The drawing shows 60 data outlets. The tenancy schedule says 72. Which governs?Answer: 72 per the tenancy schedule. Drawing to be updated.Job 10438Level 3 fit-out power and dataSam OkaforAngela PapadakisProject manager17/10/202624/10/202622/10/20265Answered

Showing 1 to 19 of 19 RFIs